TRANSMISSION WATER MAIN REPLACEMENT - Phase I 

Background

The Fair Oaks Water District (FOWD) plans to install 3,300 feet of new 24-inch ductile iron pipe in portions of Blue Oak Drive, Madison Avenue, and Winding Oak Drive to replace its existing transmission main. The existing transmission main was originally constructed in 1933 and has reached the end of its serviceable life.

What to Expect

Construction activity will begin with heavy equipment and materials appearing at the site, highlighted in red on the map below, in June of 2025. At times FOWD’s contractor may need to close access to sections of Blue Oak Drive, Madison Avenue, Winding Oak Drive, and the Rollingwood Condominium Complex for the safety of the public and their staff. Construction may cause unavoidable short-term inconvenience to residents and businesses in the immediate vicinity. The FOWD will attempt to provide 48-hour notice to anyone that will have an interruption in their water service. Work will generally occur from 8 am – 4:30 pm weekdays. Construction is estimated to take approximately 20 weeks. We appreciate your understanding as we make these improvements.

Thank you for your understanding and cooperation!

 

Transmission Main Phase I Informational.PDF
Fair Oaks Water District plans water main replacement on Blue Oak Dr, Madison Ave, Winding Oak Dr, starting June 2025, lasting 20 weeks.
Click image to view PDF

We understand that construction activities are disruptive to daily routine. We will strive to minimize the inconvenience and expedite construction. Please contact us if you have any questions or concerns during this project. We are here to help. 

(916)967-5723